Copenhagen’s M5 metro line has been approved, but no part of it is open, and the first passengers are not expected until 2036. The Government and the City of Copenhagen agreed in March 2025 to build a nine-station line from Copenhagen Central Station across Amager to Lynetteholm, with six stations in a first phase opening in 2036 and three more, at Refshaleoen and on Lynetteholm, in a second phase expected in 2045. For travellers, the value is not a new ride to book now. It is a clear map of how harbour trips, Amager stays and visits to the new East Harbour districts will change once the line is running.

Quick Facts

  • Line: M5, a new Copenhagen Metro line approved in March 2025
  • Route: Copenhagen Central Station across Amager to Lynetteholm, nine stations in total
  • Phase 1, expected 2036: Six stations, five underground and one elevated, Central Station to Prags Boulevard East
  • Phase 2, expected 2045: Three stations, Refshaleoen, Lynetteholm S and Lynetteholm N
  • Interchanges: Central Station for M3 and M4, DR Byen for M1, Lergravsparken for M2
  • Status: Approved, with construction law, environmental permit, tendering and construction still ahead
  • Source checked 18 November 2026: Metroselskabet, M5 project and news pages

What Has Actually Been Approved?

The approval is a political agreement between the Government and the City of Copenhagen to construct the M5, announced by Metroselskabet on 28 March 2025. Metroselskabet’s M5 announcement describes a new metro line with nine stations between Copenhagen Central Station and Lynetteholm across Amager, expected to open in two stages in 2036 and 2045. That is a decision to build, not a construction start, and Metroselskabet is explicit about the work still ahead.

Before the M5 can carry passengers, the company and its advisers must complete concept design and a supplementary environmental impact assessment. A comprehensive construction law must be prepared and adopted, and the project must obtain its final permit before construction. Tender design and tendering follow, along with construction design, rerouting of supply lines and the construction itself. Travellers should therefore read 2036 as the current expected opening for Phase 1, stated by the operator, not as a guaranteed date for a trip that can be booked today.

A note on the name in the headline is also honest to make. The M5 as approved is not a complete ring line. It is a harbour-crossing line from the Central Station across Amager to the East Harbour and Lynetteholm. Its ring-like effect comes from the connections it creates and from a provision at the Central Station for a possible future extension to Oesterport through Gammel Kongevej, which Metroselskabet mentions in both its project and news material. If that extension is funded and built later, the line could form part of a larger loop. As approved today, it is a new cross-harbour axis, and that is already significant.

Which Stations Open in Phase 1, in 2036?

Metroselskabet’s M5 project page, checked for this article on 18 November 2026, lists Phase 1 as five underground stations and one elevated station. In order from the centre, they are Copenhagen Central Station, at Bryggebroen, DR Byen, at Amagerbrogade S, Lergravsparken, and at Prags Boulevard East, the elevated station. That sequence is the heart of the project for everyday travel.

Copenhagen Central Station, listed as Koebenhavn H in Danish material, is the anchor. Metroselskabet says passengers there will be able to transfer easily to metro lines M3 and M4, to long-distance, regional and S-trains, and to buses. A traveller arriving from the airport or from elsewhere in Denmark will, from 2036, be able to step from a mainline train onto the M5 and ride directly across the harbour to Amager, without the current change onto the M1 or M2 and without a bus across a bridge.

Bryggebroen serves the harbour front on the Amager side of the bridge of the same name, an area of housing, swimming and cycling routes that currently relies on buses and bikes. DR Byen is an interchange with the M1 and serves the Danish Broadcasting Corporation area and the northern edge of Oerestad. Amagerbrogade S puts a station on Amager’s main street, in established residential neighbourhoods that Metroselskabet identifies as existing urban areas that currently lack metro service. Lergravsparken is an interchange with the M2 and serves eastern Amager. Prags Boulevard East, the elevated terminus of Phase 1, serves the Kloeverparken side of the East Harbour, the first of the new development areas the line is built to unlock.

What Does the Lynetteholm Branch Add in Phase 2?

Phase 2, expected in 2045, adds three stations, at Refshaleoen, at Lynetteholm S and at Lynetteholm N. Refshaleoen is the former industrial island now known for food, culture and waterfront venues, which today requires a bus, a harbour bus, a bike ride or a long walk. Lynetteholm is the new island district being created in the East Harbour, described by Metroselskabet as part of the Oesthavnen development areas alongside Kloeverparken and Refshaleoen. Without a metro, a district of that scale would be car and bus dependent from the start. With Phase 2, it will have rail at its centre.

One detail is still open, and it is worth stating plainly. Metroselskabet’s current project page says the three Phase 2 stations may be built as either underground or elevated stations, and that the decision will be made at a later date through the political process. Earlier announcement material described them as elevated. Travellers and residents should treat the form of those stations as undecided until Metroselskabet confirms it, while the station locations and the 2045 expectation are the settled parts of the plan as currently published.

The phased plan has a travel consequence. Between 2036 and 2045, the M5 will be an Amager line ending at Prags Boulevard East. Trips to Refshaleoen in that period will still need a bus, bike or harbour connection from the Phase 1 terminus or from another line. Only from 2045, on the current expectation, does the through ride from the Central Station to Lynetteholm exist. Guides that present the full nine-station line as a single opening are compressing a nine-year gap that matters for anyone planning around a specific venue or neighbourhood.

How Does the M5 Change Harbour Trips?

The harbour is Copenhagen’s central transport problem and its central pleasure. The existing metro crossing between the centre and Amager, shared by the M1 and M2, is already busy, and Metroselskabet says the M5 will increase capacity across the entire metro network and help the metro keep pace with rising ridership, particularly on the section across the harbour, where there are already large numbers of people during rush hour. A second cross-harbour metro route means a disruption or a crowded peak on one crossing no longer defines every centre to Amager trip.

For visitors, the change shows up in three familiar trips. First, Amager Strand and the eastern Amager neighbourhoods become easier from the Central Station, via Lergravsparken and the M2 interchange or via the new Amagerbrogade station for the streets west of the beach. Second, Oerestad and DR Byen gain a second metro route, so a concert or conference trip no longer depends solely on the M1. Third, the East Harbour, Kloeverparken, Refshaleoen and eventually Lynetteholm, moves from special-trip territory, planned around a bus timetable or a bike ride, to ordinary metro territory. That shift, more than any single journey time, is what a new metro line does to how visitors use a city.

None of that changes a trip taken this year. Copenhagen today still has four metro lines, and the practical advice in Where to Eat in Copenhagen: New Nordic, Smorrebrod and Michelin Value, by Neighborhood remains the right way to plan an Amager food day now, using the M1, M2 and buses. The M5 is a reason to return, and a reason the Amager side of the city will feel closer when it opens, not a tool for a current itinerary.

Why Build a Metro to a District That Does Not Exist Yet?

Lynetteholm is the clearest example in Copenhagen of infrastructure leading development rather than following it. Metroselskabet frames the M5 as serving both existing urban areas that lack metro service on Amager and new urban development areas in the East Harbour, including Kloeverparken, Refshaleoen and Lynetteholm. The line is also part of a comprehensive political agreement between the Government and the City of Copenhagen on urban development and infrastructure for Lynetteholm. In other words, the metro and the district are one policy, not two. The island is planned on the assumption that residents and workers will arrive by metro, bike and bus, and the metro is funded on the assumption that the island will generate the ridership.

Travellers who know other Nordic capitals will recognise the pattern. New harbour districts work best when the rail line is there from the first occupation, not retrofitted a decade later. The comparison with First Time in Oslo: A 3-Day Itinerary for Fjords, Saunas and New Nordic Design is instructive, because Oslo’s waterfront growth has similarly been organised around rail and tram access from the start. Copenhagen’s bet with the M5 and Lynetteholm is the same bet, made at larger scale and over a longer timeline.

Metroselskabet’s chief executive, Carsten Riis, called the decision to establish the M5 a milestone for the city and the result of extensive preparatory work in the company’s announcement. That language is corporate, but the underlying point is verifiable in the project material. Years of route choice, environmental assessment and political negotiation sit behind a nine-station line, and the remaining timeline to 2036 reflects tunnelling, station construction and systems work that cannot be compressed simply because the decision has been taken.

What Should Travellers Do With This News Now?

Do nothing differently for a trip in 2026, 2027 or the early 2030s, except to understand Amager better. Stay on Amager for value, for the beach at Amager Strandpark, for Oerestad architecture or for Refshaleoen food and culture, and use the M1, M2, buses and bikes that exist today. If a future trip falls in or after 2036, check Metroselskabet close to travel for the confirmed Phase 1 opening and for whether the Prags Boulevard East terminus pattern still applies. If a trip depends on Lynetteholm itself, treat 2045 as the current Phase 2 expectation and expect the district and its metro to evolve together over a long period.

The M5 also rewards a longer view of Copenhagen as a destination. A city that is building a new harbour district and a new metro line to serve it, while relieving the crossing that current visitors already use, is a city whose map will be noticeably different in a decade. That is a good reason to visit now, to know the harbour before it changes, and to return when the first M5 trains run under it in 2036.

Frequently Asked Questions

Is the Copenhagen M5 open now?

No. The line was approved in March 2025. Metroselskabet expects the first six stations to open in 2036 and the final three stations in 2045.

How many stations will the M5 have?

Nine stations in total, six in Phase 1 from Copenhagen Central Station to Prags Boulevard East, and three in Phase 2 at Refshaleoen, Lynetteholm S and Lynetteholm N.

Is the M5 a ring line?

Not as approved. It is a cross-harbour line from the Central Station across Amager to Lynetteholm. The Central Station will be prepared for a possible future extension to Oesterport through Gammel Kongevej, which could support a larger loop later.

Where can passengers change from the M5 to other metro lines?

At Copenhagen Central Station for M3 and M4, at DR Byen for M1, and at Lergravsparken for M2, according to Metroselskabet.

Why does the M5 serve Lynetteholm if the district is new?

The line and the district are part of the same Government and City of Copenhagen agreement on urban development and infrastructure for Lynetteholm, so the metro is planned to serve the East Harbour development areas from the start.

Featured image: Copenhagen Metro passengers from Metroselskabet, the operator’s M5 project media. Source: Metroselskabet. Facts checked against Metroselskabet primary sources on 18 November 2026.

Avatar photo

Written by Aiko Tanaka

Aiko Tanaka is Always Packed's Japan and East Asia editor. She covers the region station by station and season by season: ryokan and onsen culture, snow country, autumn leaves, and the etiquette that genuinely changes a trip. Aiko's guides are exact about the things travellers get wrong, from luggage forwarding to last trains, and she has no patience for calling a place a hidden gem when it welcomes ten million visitors a year. Precision is her love language; vagueness is her enemy. This profile is an Always Packed editorial desk, a named collection of editors and researchers publishing under a shared beat and voice.