Vancouver’s Broadway Subway is not open, and its opening window is the single fact that organises everything else about it. The Broadway Subway Project, the official project office delivering the work for the Province of British Columbia, describes a 5.7 kilometre extension of the Millennium Line from VCC-Clark Station to Broadway and Arbutus, with six new underground stations, and states that the new line is expected to go into service in fall 2027. The terminus for now is Arbutus Street, deliberately: the station there is designed to allow a future phase of rapid transit onward to the University of British Columbia, but that extension is a separate, later project that is still in planning, and no opening date exists for it. Visitors in 2026 and most of 2027 ride the existing SkyTrain network and the 99 B-Line bus, which the subway will partly replace, and anyone choosing a hotel or a rental for its Broadway Subway access is planning for a trip from fall 2027 onward.
Quick Facts
- Status: Under construction. The project office states the new line is expected to go into service in fall 2027.
- Route: A 5.7 kilometre Millennium Line extension from VCC-Clark Station to Broadway and Arbutus, including about 700 metres of elevated guideway at the eastern end and tunnels for the rest.
- Stations: Six new underground stations: Great Northern Way-Emily Carr, Mount Pleasant, Broadway-City Hall, Oak-VGH, South Granville and Arbutus.
- Key interchange: Broadway-City Hall, with a direct underground connection to the Canada Line at Cambie Street.
- Journey time: VCC-Clark to Arbutus in 11 minutes, saving the average transit user almost 30 minutes a day, per the project office.
- Capacity: Three times as many people as the current 99 B-Line on opening day, per the project office.
- Project cost: 2.954 billion Canadian dollars, delivered by Transportation Investment Corporation, a provincial Crown corporation.
- UBC: Not included. Arbutus connects to the 99 B-Line bus for UBC; a SkyTrain extension to UBC is a future phase in planning, with no opening date.
When does the Broadway Subway open?
Fall 2027 is the project’s own current answer. The Broadway Subway Project’s monthly status reporting and the Government of British Columbia’s project updates both use that formulation: the new line is expected to go into service in fall 2027. That wording matters. It is a season, not a day, and it follows earlier public timelines that placed the opening sooner, which is precisely why this guide treats the window rather than a date as the fact to plan around. Construction of permanent works is under way along the elevated guideway and at all six stations, street level rebuilding above the station boxes is part of the current phase of work, and testing and trial running must still precede any passenger service. A traveller booking Vancouver for summer 2027 should assume the subway is not part of the trip. A traveller booking for the winter holidays of 2027 should check the project site again before assuming either way.
What are the six stations, and what does each one serve?
From east to west, the extension leaves the existing Millennium Line at VCC-Clark, runs on elevated guideway for about 700 metres, then dives underground for the rest of the route. Great Northern Way-Emily Carr serves the False Creek Flats, Emily Carr University of Art and Design and the new St. Paul’s Hospital district taking shape there. Mount Pleasant serves the Main Street corridor, one of the city’s densest strips of independent shops, breweries and restaurants. Broadway-City Hall, at Cambie Street, is the extension’s structural keystone: a direct underground connection to the Canada Line gives the Broadway corridor a one change ride to downtown, to Richmond and to Vancouver International Airport, and puts City Hall itself on two lines.
Oak-VGH serves Vancouver General Hospital and the wider hospital district along Oak Street, the reason the project office lists world class health services among the corridor’s anchors. South Granville serves the gallery and shopping district where Broadway meets Granville Street, and the neighbourhoods of Fairview and Shaughnessy beyond it. Arbutus, at Broadway and Arbutus Street, is the western terminus: the edge of Kitsilano, a transfer point to buses including the 99 B-Line onward to UBC, and the designed starting point of any future UBC extension. Together the six stations put the Broadway corridor, which the project office identifies as the province’s second largest jobs centre, on the rapid transit map for the first time.
Why does the line stop at Arbutus instead of going to UBC?
Because that is how the project was funded and approved. The current build is a 5.7 kilometre, six station project with a 2.954 billion Canadian dollar budget, delivered by Transportation Investment Corporation with the Broadway Subway Project Corporation as design build contractor. Arbutus Station has been designed to allow for a future phase of investment to connect rapid transit to UBC, and planning work on that onward extension, roughly seven kilometres with stations proposed in the Macdonald Street, Alma Street and Jericho Lands areas before a UBC campus terminus, sits with the provincial government and TransLink as a separate business case. Surveys of regional residents have repeatedly found that a large share of people assume the subway already runs to UBC, which is the misconception most likely to strand a visitor: from fall 2027, the last leg to the university remains a bus ride on the 99 B-Line from Arbutus, shortened but not eliminated. No government source publishes an opening date for a UBC SkyTrain, and this guide does not invent one.
What changes for visitors when it opens?
The practical change is a fast east to west spine across the middle of the city. The project office puts the VCC-Clark to Arbutus ride at 11 minutes and the capacity at three times the current 99 B-Line on opening day, on a corridor where the bus is among the busiest in Canada and the United States. For visitors, that converts several awkward journeys into simple ones: Mount Pleasant’s Main Street strip becomes a two stop ride from the Canada Line; the hospital district and South Granville become realistic bases rather than bus dependent ones; and Kitsilano gains a rapid transit edge at Arbutus. Until then, the corridor experience is construction: station sites, rebuilt street sections above them and periodic traffic changes along Broadway, which the project office publishes as work notices. Our itinerary for a first time visit to Vancouver over four days is built on the network as it exists today, and travellers whose nationality needs one should also read our explainer on Canada’s eTA for visa exempt flyers before booking flights.
How should you plan a Vancouver trip around the opening window?
Use three rules. First, date your assumptions: any source giving a precise opening day for the Broadway Subway is going beyond what the project publishes, which is fall 2027. Second, separate the two projects in your head: Broadway Subway to Arbutus is funded, built and dated as a window; SkyTrain to UBC is planned, not yet funded as a construction project and undated, so never book accommodation in Point Grey on the basis of a station that does not yet have a builder. Third, watch the milestones that actually predict an opening: the shift from station construction to systems testing and trial running on the project site is the signal that fall 2027 is firming up, and the project office’s monthly status reports are the primary source for it. Travellers who time a trip for the opening itself should keep the 99 B-Line in the plan as the fallback, because it remains the corridor’s workhorse until the first passenger train runs.
Frequently asked questions
When does Vancouver’s Broadway Subway open?
The Broadway Subway Project states that the new line is expected to go into service in fall 2027. No exact opening day has been published, and earlier timelines pointed sooner, so plan around the season and recheck the official project site before a late 2027 trip.
How many stations does the Broadway Subway have?
Six, all underground: Great Northern Way-Emily Carr, Mount Pleasant, Broadway-City Hall, Oak-VGH, South Granville and Arbutus, along a 5.7 kilometre extension of the Millennium Line from VCC-Clark.
Does the Broadway Subway go to UBC?
No. It terminates at Arbutus Street, where passengers connect to the 99 B-Line bus for the University of British Columbia. Arbutus Station is designed to allow a future SkyTrain extension to UBC, but that phase is still in planning and has no opening date.
Which line is the Broadway Subway part of?
The Millennium Line. Trains will run through from the existing line at VCC-Clark, and Broadway-City Hall station adds an interchange with the Canada Line, giving a one change route to downtown, Richmond and the airport.
How long will the ride across the extension take?
Eleven minutes from VCC-Clark to Arbutus, according to the project office, which says the extension will save the average transit user almost 30 minutes a day and carry three times as many people as the current 99 B-Line on opening day.
How much does the Broadway Subway cost to build?
The project budget is 2.954 billion Canadian dollars, per the project’s official status reporting. Transportation Investment Corporation, a provincial Crown corporation, is delivering and overseeing the project.
Photo: Rebar work inside a Broadway Subway station construction site, Broadway Subway Project official website (broadwaysubway.ca), Government of British Columbia project image, used with credit. Visually verified: workers tying rebar inside the station box.