Bucharest is building its first direct rail link between the city and Henri Coandă International Airport, and as of October 2026 both halves of Metro Line M6 are physically moving: tunnelling on the southern section passed the halfway point of its drive in September 2026, and the first tunnel boring machine on the northern section made its first rotation on 21 October 2026. The line runs 14.2 kilometres from 1 Mai to Otopeni with 12 new stations, and it is not open, so if you are flying into Bucharest now, the airport train and the express bus described below remain your public transport options. One framing point before the detail: there is nothing for travellers to file or apply for here. The only costs in this story today are the fares for the existing train and bus, and the only order that matters is the construction sequence, which this explainer follows.
Quick Facts
- Project: Metro Line M6, 1 Mai to Otopeni, 14.2 kilometres of twin tunnel, 12 new stations and 12 new trains, run by Metrorex (project site: magistrala6.ro).
- South Section (Lot 1.1): 1 Mai to Tokyo, 6.6 kilometres, six new stations: Pajura, Expoziției, Piața Montreal, Gara Băneasa, Aeroport Băneasa and Tokyo, plus the existing 1 Mai station shared with line M4.
- North Section (Lot 1.2): Tokyo to Aeroport Otopeni, six stations: Washington, Paris, Bruxelles, Otopeni, Ion I.C. Brătianu and Aeroport Otopeni.
- Progress reported October 2026: Physical progress of 78 percent on the south section and 34 percent on the north, per the transport minister; south section tunnelling passed halfway in September 2026, and north section boring began on 21 October 2026.
- Contractors: Alsim Alarko and Makyol joint venture on the south (awarded March 2022); Gülermak and Somet joint venture on the north.
- Opening estimates: Industry reporting targets a 2028 opening for the full route; the transport minister’s October 2026 estimate was the first part of 2029. Treat 2029 as the safer planning assumption.
- Airport alternative today: CFR Călători trains from the airport station to Gara de Nord every 40 minutes around the clock, 20 to 25 minutes, 6.50 lei bought before boarding.
- Bus alternative: Line 100 to Piața Unirii, on the standard Bucharest metropolitan fare of 3 lei for 90 minutes of surface transport.
How is the line being built?
M6 is the Bucharest International Airport Rail Access Link, a project of national interest approved under Government Decision 496/2017 and funded from the state budget, European funds and a JICA loan. From 1 Mai, where it shares a station with the existing M4 line one stop from Gara de Nord, it runs north through District 1, under Bucureștii Noi and Băneasa, to Otopeni and the airport. The two construction sections meet at the future Tokyo station, beside Băneasa Airport and the IKEA store at the city’s northern edge.
The south section came first. Its building permit was issued in December 2023, the main site beside Tokyo station was organised from February 2024, and its refurbished earth pressure balance tunnel boring machine, 6.39 metres in diameter, has been driving the twin tunnels since April 2025 through mixed sand, clay, silt and gravel with a shallow water table. By 30 September 2026 the machine had passed the future Gara Băneasa station and reached roughly the halfway point of the 6.6 kilometre drive; its final approach will pass within about 3.5 metres of the live M4 tunnels beneath 1 Mai. Civil works on the south are scheduled for completion in 2027.
The north section is a year behind in feel. Its building permit dates from August 2024, its contractor is the Gülermak and Somet joint venture, and preparatory works ran at the six station sites before boring could start. On 21 October 2026 Metrorex announced that the first north section machine, named Sfânta Parascheva, had made the first rotation of its cutterhead from the launch shaft at the future Bruxelles station, starting towards Tokyo; a second machine, Sfânta Ecaterina, bores the parallel tunnel, and both will later be relaunched from Bruxelles towards Otopeni Airport. Bruxelles will also carry the line’s park and ride, about 500 spaces at the ring road for drivers switching to the metro.
When will it actually open?
Hold the two published estimates apart, because they do not agree. The tunnelling industry’s reporting, based on the contractors’ programme, targets completion of the south section civil works in 2027 and an opening of the full route to Henri Coandă in 2028. The transport minister, Ștefan Ovidiu Popa, speaking on 21 October 2026 as north section boring began, put physical progress at 78 percent south and 34 percent north and estimated the line for the first part of 2029. Ministers revising dates at a podium are usually closer to the current programme than contractor publicity, so plan as if 2029 is the working date and treat 2028 as the optimistic case. Either way, no part of M6 carries passengers before the whole 1 Mai to Otopeni route is ready, and Metrorex’s October 2026 announcement itself carried no opening date.
What should arriving travellers use until then?
The established option is the CFR Călători airport train, which has run since December 2020 between the Aeroport Henri Coandă station, reached from the ground floor of Arrivals, and București Nord, the Gara de Nord main station. Trains run daily around the clock at 40 minute intervals and take about 20 to 25 minutes, immune to the DN1 road traffic that slows every road option from the airport, which sits about 16.5 kilometres north of the centre. The fare is a flat 6.50 lei without a seat reservation, the tariff in force since 14 December 2025; reserving a seat adds 4.50 lei. Buy before you board, at the ticket office, the machines, online or in the CFR app, because the same ticket bought from the conductor on board costs 13 lei.
The bus alternative is line 100, the former 783, running from the airport to Piața Unirii in the centre on the ordinary metropolitan fare, 3 lei for a 90 minute ticket covering Bucharest’s surface network; it is cheaper and more central than the train, and slower whenever the road clogs. From Gara de Nord, the metro and the station’s tram and bus stops cover the last leg. For context on how airport rail projects elsewhere are sequencing the same kind of works, see our coverage of Bangkok Suvarnabhumi’s third runway operations and of Korea’s KTX-Cheongryong services.
Frequently Asked Questions
Is the Bucharest airport metro open?
No. Line M6 is under construction along its whole route. Tunnelling on the south section passed halfway in September 2026 and boring on the north section began on 21 October 2026, but no station is finished or open, and current estimates put opening in 2028 at the earliest, with the transport minister pointing to the first part of 2029.
What are the M6 stations?
Twelve new stations. South, from 1 Mai: Pajura, Expoziției, Piața Montreal, Gara Băneasa, Aeroport Băneasa and Tokyo. North, from Tokyo: Washington, Paris, Bruxelles, Otopeni, Ion I.C. Brătianu and Aeroport Otopeni. The line also uses the existing 1 Mai station, shared with M4.
How do I get from Henri Coandă Airport to central Bucharest now?
Take the CFR Călători train from the airport station to Gara de Nord, every 40 minutes around the clock, 20 to 25 minutes, 6.50 lei if bought before boarding; or bus line 100 to Piața Unirii on a 3 lei, 90 minute metropolitan ticket. Taxis and ride hailing use the airport’s official pick up arrangements.
Why does the airport train ticket cost more on board?
CFR Călători prices the airport route at 6.50 lei bought in advance through its normal channels, and 13 lei when the ticket is issued by the conductor on the train. The operator’s own guidance is explicit: buy before boarding to avoid the higher on board price.
Will M6 connect with the rest of the metro?
Yes, at 1 Mai, where M6 shares the station with line M4, one stop from Gara de Nord, giving access to the wider network. Through journeys from the airport to the old town will mean one change at 1 Mai or a walk or short ride from Gara de Nord.
Who is building and paying for M6?
Metrorex is the beneficiary and operator. The south section is built by the Alsim Alarko and Makyol joint venture and the north by Gülermak and Somet. Funding combines the Romanian state budget, European funds and a reimbursable JICA loan, under the project’s national interest designation.
Sources checked 17 November 2026: Metrorex project site magistrala6.ro, including the south section station list, permits and funding structure, and Metrorex’s 21 October 2026 announcement of the start of north section tunnelling as carried in Romanian press reporting with the transport minister’s progress figures; TERRATEC and tunnelling trade reporting of 30 September 2026 on south section progress; CFR Călători’s published airport route fares and conditions; Bucharest transport authority fare information for line 100. Estimates and fares can change; verify with Metrorex and CFR Călători before travelling.